NEW DELHI, 8 Apr: The Union Cabinet Committee on Economic Affairs has approved major investments for two hydroelectric projects in Arunachal Pradesh, together amounting to over Rs. 40,000 crore, aimed at boosting power generation and strengthening infrastructure in the region.
The Cabinet cleared Rs. 26,069.50 crore for the 1720 MW Kamala Hydro Electric Project (HEP), to be constructed across Kamle, Kra Daadi, and Kurung Kumey districts, with an estimated completion period of 96 months.
The project will comprise eight units of 210 MW each and one unit of 40 MW, generating 6870 million units (MU) of electricity annually.
The Kamala project will be developed through a joint venture between NHPC Limited and the government of Arunachal Pradesh.
New Delhi, April 9: The Union Cabinet on Wednesday approved investments totalling Rs 40,150 crore for the construction of two major hydropower projects in Arunachal Pradesh, as the government accelerates development of renewable energy and regional infrastructure.
The Kamala Hydro Electric Project (1,720 MW) will be built across Kamle, Kra Daadi, and Kurung Kumey districts through a joint venture between state-owned NHPC Ltd and the state government, with a planned completion period of eight years.
“The Cabinet Committee on Economic Affairs, chaired by the Prime Minister Narendra Modi, has approved investment of Rs 26,069.50 crore for the construction of Kamala Hydro Electric Project (HEP) in Kamle, Kra Daadi & Kurung Kumey districts of Arunachal Pradesh,” an official statement said, adding the estimated completion period for the project is 96 months.
The plant is expected to generate about 6,870 million units of electricity annually, supporting peak demand management, national grid balancing, and flood moderation in the Brahmaputra basin.
The Cabinet Committee on Economic Affairs (CCEA), chaired by Prime Minister Narendra Modi, has approved an investment of Rs 26,069.50 crore for the construction of the 1720 MW Kamala Hydro Electric Project (HEP) in the Kamle, Kra Daadi and Kurung Kumey districts of Arunachal Pradesh.
The estimated completion period of the project is 96 months.
Project Details and Benefits
The Kamala HEP, with an installed capacity of 1720 MW (8 x 210 MW + 1 x 40 MW), is expected to generate 6,870 million units (MU) of clean energy annually.
NHPC gains after CCEA clears Rs 26,069 -cr Hydro Electric Project in Arunachal Pradesh
NHPC gains after CCEA clears Rs 26,069 -cr Hydro Electric Project in Arunachal Pradesh
NHPC rose 1.11% to Rs 77.52 after Cabinet Committee on Economic Affairs (CCEA) has approved an investment of Rs 26,069.50 Crore for the construction of Kamala Hydro Electric Project (HEP) in Kamle, Kra Daadi & Kurung Kumey, Arunachal Pradesh.
The project will be implemented through a joint venture company between NHPC and the Govt.
The Union Cabinet on Wednesday approved investments of ₹40,150 crore for two hydropower projects in Arunachal Pradesh and revised the cost of the HPCL Rajasthan Refinery project to ₹79,459 crore, according to an official statement.
The Cabinet Committee on Economic Affairs (CCEA), chaired by Prime Minister Narendra Modi, approved ₹26,069.50 crore for the 1,720 MW Kamala Hydro Electric Project and ₹14,105.83 crore for the 1,200 MW Kalai-II Hydro Electric Project.
“The Cabinet Committee on Economic Affairs… has approved investment of ₹26,069.50 crore for construction of Kamala Hydro Electric Project (HEP)… The estimated completion period for the project is 96 months,” the statement said.
The Kamala project will be developed in Kamle, Kra Daadi and Kurung Kumey districts through a joint venture between NHPC Ltd and the Arunachal Pradesh government.
The Union Cabinet, chaired by Prime Minister Narendra Modi, on Wednesday cleared the Jaipur Metro Phase-2 project, a 41-km North-South corridor from Prahladpura to Todi Mod, at a cost of ₹13,037.66 crore, Union minister Ashwini Vaishnaw during at a post-meeting media briefing.
The 50:50 Centre-state joint venture, to be executed by Rajasthan Metro Rail Corporation Limited (RMRCL), is expected to be completed by September 2031.
“Jaipur has emerged as a major hub for tourism, conferences, healthcare and education, and its proximity to New Delhi further adds to its importance. Keeping all these factors in mind, Phase 2 is being taken up,” Vaishnaw said.
Spanning 36 stations — including 34 elevated and two underground — the corridor will link high-traffic areas such as Sitapura Industrial Area, VKIA, Tonk Road, SMS Hospital, Stadium, Ambabari and Vidhyadhar Nagar.
New Delhi [India], April 9 (ANI): The Cabinet Committee on Economic Affairs (CCEA), chaired by Prime Minister Narendra Modi, has approved an investment of Rs 26,069.50 crore for the construction of the 1720 MW Kamala Hydro Electric Project (HEP) in the Kamle, Kra Daadi and Kurung Kumey districts of Arunachal Pradesh.
The estimated completion period of the project is 96 months.
The Kamala HEP, with an installed capacity of 1720 MW (8 x 210 MW + 1 x 40 MW), is expected to generate 6,870 million units (MU) of clean energy annually.
The project will help strengthen the power supply position in Arunachal Pradesh, support peak demand management, contribute to national grid balancing and provide flood moderation benefits in the Brahmaputra valley, a release said.
The Union Cabinet has approved investment proposals worth around Rs 40,000 crore for the construction of two major hydroelectric projects in Arunachal Pradesh, marking a significant push for power generation and infrastructure development in the northeast.
Both projects will be implemented through joint ventures between central public sector undertakings and the Arunachal Pradesh government.
The Cabinet cleared an investment of Rs 26,069 crore for the 1,720 MW Kamala Hydroelectric Project, located in Kamle across the Kra Daadi and Kurung Kumey districts.
The project will be developed through a joint venture between NHPC Limited and the Government of Arunachal Pradesh, with an estimated completion timeline of 96 months.