Subansiri Lower Hydroelectric Project: Subansiri hydro project powers ahead, reaches 750 MW operational capacity | Guwahati News - The Times of India (opens in a new tab)
NHPC Limited has declared the successful commercial operation of the third unit of India’s largest hydropower project, the 2000 MW Subansiri Lower Hydroelectric Project (SLHEP), straddling the Arunachal Pradesh-Assam border, marking a significant step forward in the country’s clean energy ambitions. The newly commissioned unit — Unit 1 of 250 MW capacity — began commercial operation on Friday, injecting an additional 250 MW of clean hydropower into the National Grid. Its successful launch follows the completion of a trial run on Feb 27, which had served as a key precursor to full commercial operation. With this milestone, the Subansiri Lower Hydroelectric Project has now achieved a cumulative operational capacity of 750 MW out of its total planned capacity of 2000 MW, which will eventually be generated through eight units of 250 MW each.