£377m spent saving blast furnaces months after Port Talbot closure (opens in a new tab)
The UK Government spent £377 million to prevent the closure of the country’s last remaining blast furnaces at British Steel’s Scunthorpe plant, according to a new report. The emergency intervention came less than a year after the shutdown of the final coal-fired blast furnace at Port Talbot, which ended more than a century of primary steelmaking at the UK’s largest steelworks. A report by the National Audit Office (NAO) said the Department for Business and Trade (DBT) stepped in quickly in 2025 to keep the Scunthorpe furnaces operating, warning that their closure would have led to thousands of job losses and major disruption to key supply chains. The £377 million spent between April 2025 and January 2026 has been classified as a loan, but the NAO warned that total costs could exceed £1.5 billion by 2028 if current spending levels continue.