After 7 years of delay, Raipur Kalan-Harmilap Nagar road under bridge set to move forward | Chandigarh News - The Indian Express (opens in a new tab)
3 min readChandigarhJan 30, 2026 10:17 PM IST After remaining stalled for more than seven years, the long-pending road under bridge (RUB), a joint venture of the Indian Railways and the UT Chandigarh Administration, at the Raipur Kalan-Harmilap Nagar level crossing is finally set to move towards execution, with the Northern Railway (NR) initiating the tendering process for the project. Prolonged delays, however, significantly escalated costs. “The northern railway has invited e-bids for the construction of the RUB on the Ambala-Chandigarh rail section, to be carried out using the normal pushing technique under the running track. The bids will be opened on February 13, and once the work is allotted, the project is to be completed within 12 months,” according to the railway tender.