Calgary awards sole-source contract for feeder main replacement, work to begin this week - Calgary | Globalnews.ca (opens in a new tab)
Work to replace the ailing Bearspaw feeder main is set to begin this week, after the City of Calgary cancelled a competitive bid process and instead awarded a sole-source contract. City of Calgary Infrastructure Services general manager Michael Thompson told city council Tuesday morning that work has been accelerated after the feeder main burst twice in less than two years, with no guarantees the repaired pipe won’t break again. According to Thompson, materials were ordered on Friday and equipment and crews will be on site in the coming days. To help expedite the process, Thompson said officials made the “unprecedented” decision to cancel the competitive bid process for the replacement project and instead award a sole-source contract to Ward & Burke Microtunnelling Ltd. and Graham Construction.