Guest Post from William desRosiers at Coterra Energy.
If anyone still doubts how serious the power situation unraveling in Pennsylvania has become, the warning signs are no longer abstract.
PJM Interconnection, the regional transmission organization that coordinates wholesale electricity across all or parts of 13 states, including Pennsylvania, and the District of Columbia, made the problem unmistakably clear in its most recent capacity auction.
According to PJM’s own executive summary, the auction ended more than 6,623 megawatts (MW) below what PJM says it needed to keep the lights on safely, leaving far less backup power than recommended.
President Trump and governors of states, including those of Pennsylvania, Ohio, and Virginia, have urged PJM Interconnection LLC to hold an auction for tech companies.
President Trump and governors of states, including those of Pennsylvania, Ohio, and Virginia, have urged PJM Interconnection LLC to hold an auction for tech companies.
According to the International Energy Agency, global data center electricity consumption is expected to grow by 15% per year between 2024 and 2030.
This is more than four times faster than the growth of total electricity consumption from all other sectors, the agency said.
WASHINGTON (AP) — The Trump administration and a bipartisan group of governors on Friday tried to step up pressure on…
WASHINGTON (AP) — The Trump administration and a bipartisan group of governors on Friday tried to step up pressure on the operator of the nation’s largest electric grid to take urgent steps to boost power supplies and keep electricity bills from rising even higher.
Administration officials said doing so is essential to win the artificial intelligence race against China, even as voters raise concerns about the enormous amount of power data centers use and analysts warn of the growing possibility of blackouts in the mid-Atlantic grid in the coming years.
“We know that with the demands of AI and the power and the productivity that comes with that, it’s going to transform every job and every company and every industry,” Interior Secretary Doug Burgum told reporters at the Eisenhower Executive Office Building, next to the White House.
The Donald Trump administration will reportedly propose that PJM Interconnection, the largest power grid operator in the U.S., hold an emergency auction allowing tech giants and hyperscalers to bid on 15-year contracts for building new power plants.
The grid spans 13 states across the mid-Atlantic, Midwest, and South, including northern Virginia.
The directive is expected to be signed on Friday at the White House by the National Energy Dominance Council in the presence of Josh Shapiro, Governor of Pennsylvania, Mike DeWine, Governor of Ohio and Glenn Youngkin, Governor of Virginia, and a few other governors, reported Bloomberg on Thursday.
If PJM proceeds with the plan, it could lead to the construction of new power plants worth up to $15 billion, according to the report.
The grid operator serves more than 67 million people from the Mid-Atlantic to the Midwest
[WASHINGTON] US President Donald Trump and the governors of several US Northeastern states agreed to push for an emergency wholesale electricity auction that would compel technology companies to effectively fund new power plants.
The unprecedented plan, set to be announced on Friday (Jan 16) morning, seeks to address growing tensions over how the nation can supply electricity to power-hungry data centres, seen as necessary to help win the global artificial intelligence (AI) race, without simultaneously hiking utility bills for homes and businesses.
The Trump administration and some US governors plan to direct grid operator PJM Interconnection to hold an auction for tech companies to bid on 15-year contracts for new electricity generation capacity.
Elevate Renewables, an ArcLight portfolio company and a leading developer, owner, and operator of energy storage and hybrid generation assets, has acquired Prospect Power Storage, the largest standalone battery storage asset in the PJM Interconnection, from Swift Current Energy.
The 150 MW/600 MWh project, located in Rockingham County near Northern Virginia’s ‘Data Center Alley’, is currently under construction and scheduled to begin operations in mid-2026.
Prospect Power is fully contracted under a 15-year power purchase agreement with Dominion Energy Virginia, positioning the project as an essential energy resource to ensure cost-effective grid reliability and meet the rapidly growing demand for power across the Mid-Atlantic region.
Joshua Rogol, CEO of Elevate, commented: “The acquisition of Prospect Power underscores our commitment to building the energy infrastructure required to ensure continuous power for data centres. With its scale and strategic location within PJM, this project exemplifies the critical investments we are making to support the increased need for grid reliability and sustainability driven by growing power demand.”
The Trump administration and a bipartisan group of governors on Friday tried to step up pressure on the operator of the nation's largest electric grid to take urgent steps to boost power supplies and keep electricity bills from rising even higher.
Administration officials said doing so is essential to win the artificial intelligence race against China, even as voters raise concerns about the enormous amount of power data centers use and analysts warn of the growing possibility of blackouts in the mid-Atlantic grid in the coming years.
“We know that with the demands of AI and the power and the productivity that comes with that, it’s going to transform every job and every company and every industry,” Interior Secretary Doug Burgum told reporters at the Eisenhower Executive Office Building, next to the White House.
“But we need to be able to power that in the race that we are in against China.”
President Donald Trump and the governors of several US Northeastern states agreed to push for an emergency wholesale electricity auction that would compel technology companies to effectively fund new power plants.
The unprecedented plan, set to be announced Friday morning, seeks to address growing tensions over how the nation can supply electricity to power-hungry data centers — seen as necessary to help win the global AI race — without simultaneously hiking utility bills for homes and businesses.
The Trump administration and some US governors plan to direct grid operator PJM Interconnection LLC to hold an auction for tech companies to bid on 15-year contracts for new electricity generation capacity.
If the auction proceeds as envisaged, tech giants would pay for power over the duration of the contracts, whether they use the electricity or not, providing secure revenues for years in a market notorious for price volatility and generator bankruptcies.
United States President Donald Trump, together with governors from several Northeastern states, is set to announce an emergency wholesale electricity auction on Friday, according to Bloomberg.
The move could require American technology companies to fund new power plants.
The surprise plan, which Bloomberg reported will be announced Friday morning, comes amid growing tension over how the US can supply electricity to power-hungry data centres without hiking bills for households and businesses.
Data centres have become an absolute necessity for tech companies aggressively pushing AI to gain an edge in the global race.
Trump to propose plan for tech companies to fund new power plants
4 min read
16 Jan 2026, 02:49 pm IST
The White House proposal, set to be announced Friday, would involve an emergency auction within the country’s biggest power market.
President Donald Trump and the governors of several US Northeastern states agreed to push for an emergency wholesale electricity auction that would compel technology companies to effectively fund new power plants.
The unprecedented plan, set to be announced Friday morning, seeks to address growing tensions over how the nation can supply electricity to power-hungry data centers - seen as necessary to help win the global AI race - without simultaneously hiking utility bills for homes and businesses.
The Trump administration and some US governors plan to direct grid operator PJM Interconnection LLC to hold an auction for tech companies to bid on 15-year contracts for new electricity generation capacity.
If the auction proceeds as envisaged, tech giants would pay for power over the duration of the contracts, whether they use the electricity or not, providing secure revenues for years in a market notorious for price volatility and generator bankruptcies.