Jan 9, 2026 (AP) – Social media giant Meta on Friday announced it had cut a trio of deals to power its artificial intelligence data centers, less than one day after Elon Musk's artificial intelligence company xAI announced being set to spend $20 billion to build a data center in Southaven, Mississippi.
In Mississippi, Gov. Tate Reeves announced the xAI deal on Thursday, calling it the largest private investment in the state's history.
Meta’s energy deals constitute enough power to light up the equivalent of about 5 million homes.
The parent company of Facebook announced agreements with TerraPower, Oklo and Vistra for nuclear power for its Prometheus AI data center that is being built in New Albany, Ohio.
surged early Friday after the nuclear company announced a new agreement with Facebook-parent Meta Platforms that ties the company directly to Meta’s expanding artificial intelligence infrastructure.
Oklo stock today jumps as Meta deal fuels AI-driven nuclear demand
The rally came as Meta revealed two nuclear power deals aimed at securing long-term, clean energy for its data center operations.
While one agreement involved S&P 500 utility Vistra, investors focused sharply on Oklo’s role in supporting Meta’s AI ambitions.
(Headline USA)
Meta has cut a trio of deals to power its artificial intelligence data centers, securing enough energy to light up the equivalent of about 5 million homes.
The parent company of Facebook on Friday announced agreements with TerraPower, Oklo and Vistra for nuclear power for its Prometheus AI data center that is being built in New Albany, Ohio.
Meta announced Prometheus, which will be a 1-gigawatt cluster spanning across multiple data center buildings, in July.
Facebook parent Meta has reached nuclear power deals with three companies as it continues to look for electricity sources for its artificial intelligence data centers.
Meta struck agreements with TerraPower, Oklo and Vistra for nuclear power for its Prometheus AI data center that is being built in New Albany, Ohio.
Meta announced Prometheus, which will be a 1-gigawatt cluster spanning across multiple data center buildings, in July.
It’s anticipated to come online this year.
Facebook's parent company signs deals with three companies to extend the life of existing nuclear plants and develop new reactor technologies.
Meta has signed 20-year contracts with energy company Vistra to purchase power from three nuclear plants in Ohio and Pennsylvania.
The company will also provide financial backing for the development of Small Modular Reactors (SMRs) at Oklo and TerraPower.
The projects are expected to deliver up to 6.6 gigawatts of capacity by 2035 - roughly equivalent to six or seven conventional nuclear plants.
Facebook parent Meta says it has reached nuclear power deals with three companies as it continues to look for electricity sources for its artificial intelligence data centres.
Meta struck agreements with TerraPower, Oklo and Vistra for nuclear power for its Prometheus AI data centre that is being built in New Albany, Ohio.
Meta announced Prometheus, which will be a 1-gigawatt cluster spanning across multiple data centre buildings, in July.
It is anticipated to come online this year.
Meta has announced agreements with three nuclear power providers as the company aims to secure necessary resources for its AI ambitions.
The Facebook-parent company has struck deals with Vistra, TerraPower and Oklo – all of which are working on nuclear power technologies.
The company wants to use the power for Meta’s Prometheus supercluster computing system that’s being built at a data centre in New Albany, Ohio.
Meta CEO Mark Zuckerberg first unveiled the Prometheus project in July, identifying it as the foundational infrastructure for developing “superintelligence.”
Meta has cut a trio of deals to power its artificial intelligence data centers, securing enough energy to light up…
Meta has cut a trio of deals to power its artificial intelligence data centers, securing enough energy to light up the equivalent of about 5 million homes.
The parent company of Facebook on Friday announced agreements with TerraPower, Oklo and Vistra for nuclear power for its Prometheus AI data center that is being built in New Albany, Ohio.
Meta announced Prometheus, which will be a 1-gigawatt cluster spanning across multiple data center buildings, in July.
Meta has cut a trio of deals to power its artificial intelligence data centers, securing enough energy to light up the equivalent of about 5 million homes.
The parent company of Facebook on Friday announced agreements with TerraPower, Oklo and Vistra for nuclear power for its Prometheus AI data center that is being built in New Albany, Ohio.
Meta announced Prometheus, which will be a 1-gigawatt cluster spanning across multiple data center buildings, in July.
It's anticipated to come online this year.
Oklo Inc. (NYSE:OKLO) stock rose Friday after the company announced a strategic partnership with Meta Platforms, Inc. (NASDAQ:META), underscoring growing demand for reliable, clean power to support large-scale data center expansion.
Power Campus Deal With Meta
The agreement advances Oklo’s plan to develop a 1.2-gigawatt power campus in Pike County, Ohio, designed to supply electricity to Meta’s regional data center operations.
The project will be built on a 206-acre site in Pike County, previously owned by the Department of Energy and now held by Oklo.
Meta has cut a trio of deals to power its artificial intelligence data centers, securing enough energy to light up the equivalent of about 5 million homes.
The parent company of Facebook on Friday announced agreements with TerraPower, Oklo and Vistra for nuclear power for its Prometheus AI data center that is being built in New Albany, Ohio.
Meta announced Prometheus, which will be a 1-gigawatt cluster spanning across multiple data center buildings, in July.
It's anticipated to come online this year.
Meta lines up massive supply of nuclear power to energize AI data centers
Meta buys nuclear power
Michelle Chapman, The Associated Press - Jan 9, 2026 / 10:08 am | Story: 593321
Photo: The Canadian Press
Meta has cut a trio of deals to power its artificial intelligence data centers, securing enough energy to light up the equivalent of about 5 million homes.
The parent company of Facebook on Friday announced agreements with TerraPower, Oklo and Vistra for nuclear power for its Prometheus AI data center that is being built in New Albany, Ohio.
Meta announced Prometheus, which will be a 1-gigawatt cluster spanning across multiple data center buildings, in July.
It's anticipated to come online this year.
Meta has cut a trio of deals to power its artificial intelligence data centers, securing enough energy to light up the equivalent of about 5 million homes.
The parent company of Facebook on Friday announced agreements with TerraPower, Oklo and Vistra for nuclear power for its Prometheus AI data center that is being built in New Albany, Ohio.
Meta announced Prometheus, which will be a 1-gigawatt cluster spanning across multiple data center buildings, in July.
It's anticipated to come online this year.
WASHINGTON, Jan 9 : Meta Platforms said on Friday it struck 20-year agreements to buy power from three Vistra nuclear plants in the U.S. heartland and develop projects with two companies hoping to build small modular reactors.
Shares of Oklo surged nearly 20 per cent, whereas Vistra rose about 8 per cent in premarket trade.
Meta and other Big Tech companies want to secure long-term electricity supplies as artificial intelligence and data centers increase U.S. power demand for the first time in two decades.
The company said in a blog it will purchase power from Vistra's Perry and Davis-Besse plants in Ohio and Beaver Valley plant in Pennsylvania.
Financial terms of the deals with TerraPower, Oklo and Vistra were not disclosed.
The Mark Zuckerberg-led Meta said in a statement on Friday that the three deals will support up to 6.6 gigawatts of new and existing clean energy by 2035.
A single gigawatt, according to a general industry standard for utilities, can power about 750,000 homes.
“These projects add reliable and firm power to the grid, reinforce America’s nuclear supply chain, and support new and existing jobs to build and operate American power plants,” the company said.
Mark Zuckerberg is betting big on nuclear power to fuel his AI strategy.
Meta is working with three partners: Bill Gates-backed TerraPower and Oklo to build new facilities, while buying electricity from Vistra’s trio of plants in Pennsylvania and Ohio, according to The Wall Street Journal.
Meta wants the new reactors up and running between 2030 and 2032, which is an ambitious schedule for nuclear projects.
But Wall Street loved the news, sending Vistra and Oklo shares up 15 percent.
Meta Platforms has positioned itself as one of America's most significant corporate purchasers of nuclear energy after announcing a series of deals that could supply more than 6 gigawatts of electricity—enough to power roughly 5 million homes.
The move, aimed at securing reliable power for the company's massive artificial intelligence infrastructure, sent shares of nuclear developer Oklo soaring by up to 20 per cent in early trading on Friday.
The agreement highlights the immense energy demands of Big Tech and the high costs associated with powering the future of AI.
Oklo Lands Landmark 1.2-Gigawatt Ohio Deal
Meta has cut a trio of deals to power its artificial intelligence data centers, securing enough energy to light up the equivalent of about 5 million homes.
The parent company of Facebook on Friday announced agreements with TerraPower, Oklo and Vistra for nuclear power for its Prometheus AI data center that is being built in New Albany, Ohio.
Meta announced Prometheus, which will be a 1-gigawatt cluster spanning across multiple data center buildings, in July.
It's anticipated to come online this year.