Vijayawada: Following a dismal response to its earlier tender notification for the completion of the balance works of the new integrated terminal building and associated facilities at Vijayawada International Airport, the Airports Authority of India (AAI) floated a fresh tender inviting contractors to complete the remaining works at an estimated cost of Rs 138.20 crore.
The new integrated terminal building works at the airport were 80% complete, while the remaining 20% works, which are pending, are likely to take another 5 months for completion, further delaying its construction and pushing the terminal building inauguration to the second half of 2026.
To cater to the growing air and passenger traffic and to further enhance the passenger amenities at Vijayawada airport, the foundation stone for the construction of the Rs 611 crore new integrated terminal building at Vijayawada International Airport was laid on December 4, 2018, by the then civil aviation minister Suresh Prabhu and former vice-president M Venkaiah Naidu.
The terminal building was under construction ever since its foundation stone, missing multiple deadlines.
Strike affects banking services
Vijayawada: Asper the call given by the United Forum of Bank Unions (UFBU), a one-day nationwide strike was observed in NTR and Krishna districts on Tuesday.
As a result, banking services were suspended in these two districts.
In Vijayawada, massive demonstrations were held in front of the Union Bank of India Regional Office in One Town and Dharna Chowk.
A large number of bank employees and officers took part, demanding the immediate implementation of the five-day work week.
Vijayawada: IT and HRD minister Nara Lokesh met Tech Mahindra CEO and MD Mohit Joshi in Davos, seeking faster execution of the company’s proposed IT campus in Vijayawada, expected to employ 5,000–10,000 professionals, and expansion of delivery operations in Visakhapatnam.
He also proposed a Tech Mahindra skilling campus focused on AI, ML, Cloud IoT, cybersecurity, and Industry 4.0, alongside startup mentoring through the Ratan Tata Innovation Hub.
He pitched a Centre of Excellence at IIT Tirupati and a Quantum Computing Lab in the Amaravati Quantum Valley.
Joshi said Tech Mahindra would review the proposals, citing its partnership with Andhra Pradesh on India’s first statewide Cybersecurity Operations Centre.
Vijayawada: Thick fog disrupted flight operations at Vijayawada International Airport in the early hours of Monday, delaying the arrival of four flights by one to two hours, while one flight was cancelled.
Airport authorities said all flights scheduled to land in the early morning could do so only after 10 am, once visibility improved.
The delayed flights included an Air India service from Delhi, an Air India Express flight from Bengaluru and two IndiGo flights from Hyderabad and Chennai.Meanwhile, an Air India Express flight operating from Visakhapatnam to Vijayawada was cancelled due to poor visibility caused by the fog.
Vijayawada: The revised March 31, 2026 deadline for the completion of the new integrated terminal building at Vijayawada International Airport is unlikely to be met once again, as the Airports Authority of India (AAI) is yet to onboard a contracting agency to complete the pending works.
Construction of the Rs 611-crore integrated terminal building at Vijayawada airport originally commenced in Dec 2018 and achieved only about 80% progress so far.
"While the deadline to complete terminal building construction is March 31, the contract firms which attended the pre-bid query meetings asked the AAI to extend the work completion period from 3 months to 6 months, as they think it would take at least 6 months for them to finish the pending construction works before handing it over to the AAI," said an AAI official at Vijayawada International Airport, requesting anonymity.
According to the earlier revised deadline, the construction works of the terminal building were to be completed by March 31, and thereafter it will take about 2 months to commission the building.
Vijayawada: Chief minister Nara Chandrababu Naidu on Saturday said drones manufactured in Kurnool district of Andhra Pradesh were successfully used in Operation Sindoor.
Highlighting the growing technological capabilities of the state, he asserted that AP would emerge as a major hub for advanced drone development, with future-ready technology designed to serve multiple civilian and strategic needs.
Addressing the golden jubilee celebrations of Siddhartha Academy in Vijayawada, the chief minister said his govt is committed to ensure balanced development across all three regions of the state.
He outlined major upcoming projects, including a quantum computing initiative in Amaravati, a large-scale data centre in Visakhapatnam, and a space city project in Tirupati, which he said will position AP at the forefront of innovation.
VIJAYAWADA: Heartfulness, in partnership with the Government of Andhra Pradesh, has launched a landmark Net-Zero Residential School pilot project at the APSWREIS Residential School in Kuntamukkala, near Vijayawada.
Designed as a scalable model of an Integrated Ecological Campus, the initiative aims to transform residential schools into sustainable, climate-positive learning environments.
The campus will feature green belts, wetlands, microgreens, and a rainforest, creating a closed Net-Zero loop.
Students will play a central role through “green governance,” fostering ecological responsibility and preparing them to become environmentally conscious leaders.
VIJAYAWADA: Heartfulness, in partnership with the Government of Andhra Pradesh, has launched a landmark Net-Zero Residential School pilot project at the APSWREIS Residential School in Kuntamukkala, near Vijayawada.
Designed as a scalable model of an Integrated Ecological Campus, the initiative aims to transform residential schools into sustainable, climate-positive learning environments.
The campus will feature green belts, wetlands, microgreens, and a rainforest, creating a closed Net-Zero loop.
Students will play a central role through “green governance,” fostering ecological responsibility and preparing them to become environmentally conscious leaders.