The
government awarded the 2,400 MW
(Pirpainti) power project to
after a competitive bidding process in which the Ahmedabad-based company quoted a lower electricity tariff than three other bidders, including
The Bihar government awarded the 2,400 MW Bhagalpur (Pirpainti) power project to
Ltd after a competitive bidding process in which the Ahmedabad-based company quoted a lower electricity tariff than three other bidders, including
and
, sources said.
The Bihar government awarded the 2,400 MW Bhagalpur (Pirpainti) power project to
Ltd after a competitive bidding process in which the Ahmedabad-based company quoted a lower electricity tariff than three other bidders, including
and
, sources said.
Show Quick Read
Key points generated by AI, verified by newsroom
New Delhi: The Bihar government awarded the 2,400 MW Bhagalpur (Pirpainti) power project to Adani Power Ltd after a competitive bidding process in which the Ahmedabad-based company quoted a lower electricity tariff than three other bidders, including Torrent Power and JSW Energy, sources said.
The Bihar government had floated an open tender for the Bhagalpur project to meet the state's electricity demand, projected to double to over 17,000 MW by 2034-35.
The Bihar government awarded the 2,400 MW Bhagalpur (Pirpainti) power project to Adani Power Ltd after a competitive bidding process in which the Ahmedabad-based company quoted a lower electricity tariff than three other bidders, including Torrent Power and JSW Energy, sources said.
The Bihar government had floated an open tender for the Bhagalpur project to meet the state's electricity demand, projected to double to over 17,000 MW by 2034-35.
Four qualified bidders participated in the tender, with Adani Power quoting the lowest electricity tariff of Rs 6.075 per kWh (or per unit), sources with direct knowledge of the bidding process said.
Adani Power emerged as the lowest bidder (L1) with a tariff of Rs 6.075 per kWh, comprising a fixed charge of Rs 4.165 and a fuel charge of Rs 1.91 per unit.
The Bihar government awarded the 2,400 MW Bhagalpur (Pirpainti) power project to Adani Power Ltd after a competitive bidding process in which the Ahmedabad-based company quoted a lower electricity tariff than three other bidders, including Torrent Power and JSW Energy, sources said.
The Bihar government had floated an open tender for the Bhagalpur project to meet the state's electricity demand, projected to double to over 17,000 MW by 2034-35.
Four qualified bidders participated in the tender, with Adani Power quoting the lowest electricity tariff of Rs 6.075 per kWh (or per unit), sources with direct knowledge of the bidding process said.
Adani Power emerged as the lowest bidder (L1) with a tariff of Rs 6.075 per kWh, comprising a fixed charge of Rs 4.165 and a fuel charge of Rs 1.91 per unit.
The Bihar government awarded the 2,400 MW Bhagalpur (Pirpainti) power project to Adani Power Ltd after a competitive bidding process in which the Ahmedabad-based company quoted a lower electricity tariff than three other bidders, including Torrent Power and JSW Energy, sources said.
The Bihar government had floated an open tender for the Bhagalpur project to meet the state's electricity demand, projected to double to over 17,000 MW by 2034-35.
Four qualified bidders participated in the tender, with Adani Power quoting the lowest electricity tariff of Rs 6.075 per kWh (or per unit), sources with direct knowledge of the bidding process said.
Adani Power emerged as the lowest bidder (L1) with a tariff of Rs 6.075 per kWh, comprising a fixed charge of Rs 4.165 and a fuel charge of Rs 1.91 per unit.
New Delhi: The Bihar government awarded the 2,400 MW Bhagalpur (Pirpainti) power project to Adani Power Ltd after a competitive bidding process in which the Ahmedabad-based company quoted a lower electricity tariff than three other bidders, including Torrent Power and JSW Energy, sources said.
The Bihar government had floated an open tender for the Bhagalpur project to meet the state's electricity demand, projected to double to over 17,000 MW by 2034-35.
Four qualified bidders participated in the tender, with Adani Power quoting the lowest electricity tariff of Rs 6.075 per kWh (or per unit), sources with direct knowledge of the bidding process said.
Adani Power emerged as the lowest bidder (L1) with a tariff of Rs 6.075 per kWh, comprising a fixed charge of Rs 4.165 and a fuel charge of Rs 1.91 per unit.
On Tuesday, 4 November 2025, BJP leader, former MP, and ex-Union Power Minister RK Singh levelled allegations of a ₹62,000 power scam between the Bihar government and Adani Power Ltd (APL).
The accusation was based on an earlier agreement between the state and APL of leasing 1020 acres of land at a rate of only ₹1 per acre per year for 25 years.
The charge was made during an interview with ABP News ahead of phase 1 polls of the 2025 Bihar Elections on 6 November 2025.
“This is a very big scam,” Singh said during the interview, “An agreement has been signed with Adani that for 25 years, the government will make electricity Rs 6.075 per unit. This is the agreement they have signed. Adani has been given a lot of money to install a power plant at an inflated price.”