Portland General Electric and GridCARE Accelerate Hundreds of Megawatts of Data Center Power in Leading U.S. Market - Laotian Times (opens in a new tab)
GridCARE’s AI-enabled grid planning approach accelerates time-to-power in Hillsboro, Oregon REDWOOD CITY, Calif., Oct. 8, 2025 /PRNewswire/ — Portland General Electric (PGE) and GridCARE successfully completed their first joint project to accelerate large load interconnections using flexibility for data centers in Hillsboro, Oregon. This will result in over 80 MW of incremental capacity available for data center load in 2026, part of a total of more than 400 MW that will be energized by 2029. The novel generative AI-forecasting methodology more efficiently uses existing grid infrastructure to meet growing electricity demand in key economic sectors.