Daily penalty rule forces metro contractors to bring in workers by flight, train | Mumbai news - Hindustan Times (opens in a new tab)
Mumbai: Since the Covid-19 pandemic and related restrictions hit labour supply across industries, contractors engaged in construction of metro rail corridors in the Mumbai Metropolitan Region (MMR) have cited labour shortage as a key reason for delays running into months, sometimes years. But the situation has undergone a sea change after the Mumbai Metropolitan Region Development Authority (MMRDA) introduced a new penalty framework in mid-June, whereby daily fines are imposed on contractors for shortage of manpower, especially at four metro rail corridors slated for operationalisation by 2025-end. The simple rule has pushed up labour deployment at the four metro rail corridors by 17-37%. Contractors are bringing in labourers from northern and eastern India by train, and in some cases, flights, to avoid penalties and the enhanced workforce is speeding up work considerably, sources in the MMRDA told Hindustan Times.