$27 million fallout? Cost of tollway bid misstep piles up (opens in a new tab)
The costs of awarding a major construction contract to the wrong company are adding up for the Illinois tollway. The agency settled a lawsuit with Judlau Construction in 2024, paying about $10 million in damages after abruptly canceling its contract to reconfigure the southbound side of the I-88/I-290 interchange. Then in April, the board approved a $16.5 million change order for replacement contractor, Walsh Construction Co., to expedite the delayed project. Construction is taking place on the southbound lanes of I-290, left-center, as I-294 runs alongside in Elmhurst.