A contractor company mandated to deliver 2,100 electric buses to BEST by May 2023 has supplied only 536 buses over three years since the contract was signed, forcing the Mumbai transport service provider to operate with a reduced fleet and scaled-down services.
BEST has stated that all buses are now "proposed to be delivered" by August 2025.
The company, Olectra Greentech, attributed the delay to disruptions in the supply of battery-fitted chassis from its technology partner, BYD.
BEST buses, often considered the arteries of Mumbai's transport network, provide crucial last-mile connectivity for commuters.
In a significant breach of contract, Olectra Greentech has fallen short of delivering the 2,100 electric buses it promised to Mumbai's BEST, a shortfall that is increasingly burdening the city's already strained public transport system.
With only 536 buses supplied, the transport service is experiencing a cascade of operational challenges.
The contractor, Olectra, attributes these delays to disruptions in the delivery of battery-fitted chassis from its technology partner, BYD.
This shortage has meant prolonged waiting times and overcrowded buses for the 30 lakh passengers who rely on BEST each day.
Mumbai, A contractor company mandated to deliver 2,100 electric buses to BEST by May 2023 has supplied only 536 buses over three years since the contract was signed, forcing the Mumbai transport service provider to operate with a reduced fleet and scaled-down services.
BEST has stated that all buses are now "proposed to be delivered" by August 2025.
The company, Olectra Greentech, attributed the delay to disruptions in the supply of battery-fitted chassis from its technology partner, BYD.
BEST buses, often considered the arteries of Mumbai’s transport network, provide crucial last-mile connectivity for commuters.
Mumbai, Apr 27 (PTI) A contractor company mandated to deliver 2,100 electric buses to BEST by May 2023 has supplied only 536 buses over three years since the contract was signed, forcing the Mumbai transport service provider to operate with a reduced fleet and scaled-down services.
BEST has stated that all buses are now "proposed to be delivered" by August 2025.
Also Read | ‘This Claim Is Misleading’: Fake WhatsApp Message About Donations for Indian Army Modernisation and Welfare of Soldiers Flagged by Government.
The company, Olectra Greentech, attributed the delay to disruptions in the supply of battery-fitted chassis from its technology partner, BYD.
Mumbai, Apr 27 (PTI) A contractor company mandated to deliver 2,100 electric buses to BEST by May 2023 has supplied only 536 buses over three years since the contract was signed, forcing the Mumbai transport service provider to operate with a reduced fleet and scaled-down services.
BEST has stated that all buses are now "proposed to be delivered" by August 2025.