Microsoft said it is “slowing or pausing” some of its data center construction, including a $1 billion project in Ohio, the latest sign that the demand for artificial intelligence technology that drove a massive infrastructure expansion might not need quite as many powerful computers as expected.
The tech giant confirmed this week that it is halting early-stage projects on rural land it owns in central Ohio's Licking County, outside of Columbus, and will reserve two of the three sites for farmland.
“In recent years, demand for our cloud and AI services grew more than we could have ever anticipated and to meet this opportunity, we began executing the largest and most ambitious infrastructure scaling project in our history,” said Noelle Walsh, the president of Microsoft's cloud operations, in a post on LinkedIn.
Walsh said “any significant new endeavor at this size and scale requires agility and refinement as we learn and grow with our customers. What this means is that we are slowing or pausing some early-stage projects.”
The Atlas V rocket will launch Amazon’s Project Kuiper satellites from Cape Canaveral, Florida, on April 9, 2025, at 7 p.m.
ET.
This launch is part of a $10 billion initiative to deploy a satellite constellation enhancing global internet connectivity.
Visible from multiple locations, including cities in Ohio, the rocket’s fiery ascent may be seen across the United States and Canada, weather permitting.
Licking County, Ohio, close to Columbus, was the site Microsoft chose to build a billion-dollar networks of data centers.
Those plans will not move forward, the company now reports.
The two unmentioned elephants in the room (or perhaps in the charming covered bridge) would be the tariffs, obviously, but also cooling interest in AI.
"After careful consideration, we will not be moving forward at this time with our plans to build data centers at the Licking County sites," the company announced in a message to local news media.
said it is "slowing or pausing" some of its data center construction, including a $1 billion project in Ohio, the latest sign that the demand for artificial intelligence technology that drove a massive infrastructure expansion might not need quite as many powerful computers as expected.
The
giant confirmed this week that it is halting early-stage projects on rural land it owns in central Ohio's Licking County, outside of Columbus, and will reserve two of the three sites for farmland.
"In recent years, demand for our cloud and AI services grew more than we could have ever anticipated and to meet this opportunity, we began executing the largest and most ambitious infrastructure scaling project in our history," said Noelle Walsh, the president of Microsoft's cloud operations, in a post on LinkedIn.
Microsoft said it is “slowing or pausing” some of its data center construction, including a $1 billion project in Ohio, the latest sign that the demand for artificial intelligence technology that drove a massive infrastructure expansion might not need quite as many powerful computers as expected.
The tech giant confirmed this week that it is halting early-stage projects on rural land it owns in central Ohio’s Licking County, outside of Columbus, and will reserve two of the three sites for farmland.
“In recent years, demand for our cloud and AI services grew more than we could have ever anticipated and to meet this opportunity, we began executing the largest and most ambitious infrastructure scaling project in our history,” said Noelle Walsh, the president of Microsoft’s cloud operations, in a post on LinkedIn.
Walsh said “any significant new endeavor at this size and scale requires agility and refinement as we learn and grow with our customers. What this means is that we are slowing or pausing some early-stage projects.”
OHIO — Cans of honey roasted peanuts are being recalled at Heinen's Grocery stores in Ohio and Illinois due to the possible presence of cashews.
Trophy Nut Company of Tipp City, Ohio, issued the recall for its Heinen's 8.25-ounce cans of Honey Roasted Peanuts, and people who have an allergy or severe sensitivity to cashews are at risk.
The peanuts have a "best if used by" date of Oct. 1, 2025 and a "best by" date of Oct. 3, 2025 on the bottom of the can.
The UPC is 20601401877, which can be found on the label.
Microsoft said it is “slowing or pausing” some of its data center construction, including a $1 billion project in Ohio, the latest sign that the demand for artificial intelligence technology that drove a massive infrastructure expansion might not need quite as many powerful computers as expected.
What You Need To Know
Microsoft says it's “slowing or pausing” some of data center construction, including a $1 billion project in Ohio
It's the latest sign that the demand for artificial intelligence technology that drove a massive infrastructure expansion might not need quite as many powerful computers as expected
AP Technology Writer (AP) — Microsoft (MSFT) said it is “slowing or pausing” some of its data center construction, including a $1 billion project in Ohio, the latest sign that the demand for artificial intelligence technology that drove a massive infrastructure expansion might not need quite as many powerful computers as expected.
The tech giant confirmed this week that it is halting early-stage projects on rural land it owns in central Ohio’s Licking County, outside of Columbus, and will reserve two of the three sites for farmland.
“In recent years, demand for our cloud and AI services grew more than we could have ever anticipated and to meet this opportunity, we began executing the largest and most ambitious infrastructure scaling project in our history,” said Noelle Walsh, the president of Microsoft’s cloud operations, in a post on LinkedIn.
NasdaqGS – Nasdaq Real Time Price • USD
This article comes from Canary Media’s Ohio Utility Watch newsletter, a monthly update on Ohio’s HB6 power plant bailout scandal.
Visit our newsletter page to sign up.
Welcome to Ohio Utility Watch, a newsletter tracking Ohio’s ongoing public-corruption saga, often referred to as the House Bill 6 or HB 6 scandal.
If you’re new to the story, it revolves around the use of dark money by utility companies and others to pass roughly $60 million in bribes to secure more than $1.5 billion in ratepayer subsidies for aging, uneconomical coal and nuclear power plants.
The Ohio Corn & Wheat Growers Association, alongside farmers, national agricultural advocates, and ethanol industry leaders, praised Lieutenant Governor Jim Tressel for his recent letter to Ohio’s congressional delegation urging them to support federal legislation to expand access to E15 fuel nationwide.
In his letter, Lt. Governor Tressel called for amending the Clean Air Act to offer a permanent solution to enable year-round E15 sales.
This move would boost rural economies, promote sustainable energy, and increase demand for homegrown ethanol.
“On behalf of the Ohio Corn & Wheat Growers Association, I want to extend our gratitude to Lt. Governor Jim Tressel for his leadership and support of Ohio farmers,” shared Tyler Drewes, President of the Ohio Corn & Wheat Growers Association.
AP Technology Writer (AP) — Microsoft said it is “slowing or pausing” some of its data center construction, including a…
AP Technology Writer (AP) — Microsoft said it is “slowing or pausing” some of its data center construction, including a $1 billion project in Ohio, the latest sign that the demand for artificial intelligence technology that drove a massive infrastructure expansion might not need quite as many powerful computers as expected.
The tech giant confirmed this week that it is halting early-stage projects on rural land it owns in central Ohio’s Licking County, outside of Columbus, and will reserve two of the three sites for farmland.
“In recent years, demand for our cloud and AI services grew more than we could have ever anticipated and to meet this opportunity, we began executing the largest and most ambitious infrastructure scaling project in our history,” said Noelle Walsh, the president of Microsoft’s cloud operations, in a post on LinkedIn.
AP Technology Writer — (AP) — Microsoft said it is “slowing or pausing” some of its data center construction, including a $1 billion project in Ohio, the latest sign that the demand for artificial intelligence technology that drove a massive infrastructure expansion might not need quite as many powerful computers as expected.
The tech giant confirmed this week that it is halting early-stage projects on rural land it owns in central Ohio's Licking County, outside of Columbus, and will reserve two of the three sites for farmland.
“In recent years, demand for our cloud and AI services grew more than we could have ever anticipated and to meet this opportunity, we began executing the largest and most ambitious infrastructure scaling project in our history,” said Noelle Walsh, the president of Microsoft's cloud operations, in a post on LinkedIn.
Walsh said “any significant new endeavor at this size and scale requires agility and refinement as we learn and grow with our customers. What this means is that we are slowing or pausing some early-stage projects.”
COLUMBUS, Ohio, April 7, 2025 /PRNewswire/ -- CAS, a division of the American Chemical Society specializing in scientific content and knowledge management, and Cleveland Clinic, an academic health system with a global footprint, announced plans for a strategic collaboration that will unite the organizations' unique expertise, technology, and data capabilities to fuel clinical research.
During the Cleveland Discovery & Innovation Forum, an event highlighting cutting-edge healthcare and life sciences research, the two global organizations announced that their collaboration's first strategic focus area will be aiming to advance research on health, wellness, and healthy aging.
Initial projects the organizations are discussing will focus on drug discovery for brain health, a priority underscored by the relative lack of effective, disease-modifying treatments for Alzheimer's due to the complex nature of the disease.
"This unique collaboration leverages Cleveland Clinic's expertise in biomedical research and clinical care with CAS leadership in scientific data and technology," said Lara Jehi, M.D., Cleveland Clinic Chief Research Information Officer.
AP Technology Writer — (AP) — Microsoft said it is “slowing or pausing” some of its data center construction, including a $1 billion project in Ohio, the latest sign that the demand for artificial intelligence technology that drove a massive infrastructure expansion might not need quite as many powerful computers as expected.
The tech giant confirmed this week that it is halting early-stage projects on rural land it owns in central Ohio's Licking County, outside of Columbus, and will reserve two of the three sites for farmland.
“In recent years, demand for our cloud and AI services grew more than we could have ever anticipated and to meet this opportunity, we began executing the largest and most ambitious infrastructure scaling project in our history,” said Noelle Walsh, the president of Microsoft's cloud operations, in a post on LinkedIn.
Walsh said “any significant new endeavor at this size and scale requires agility and refinement as we learn and grow with our customers. What this means is that we are slowing or pausing some early-stage projects.”
(RTTNews) - Microsoft is putting the brakes on several data center projects, including a $1 billion development in Licking County, Ohio, as it reevaluates the infrastructure needed to support its growing cloud and AI operations.
The tech giant confirmed it will halt early-stage construction on the Ohio sites, reserving two of the three parcels for farmland instead.
The Ohio pause is part of a broader trend.
Microsoft previously delayed the next phases of a major Wisconsin data center and, according to analysts at TD Cowen, has also scaled back some international plans and canceled U.S. data center leases.
(RTTNews) - Microsoft is putting the brakes on several data center projects, including a $1 billion development in Licking County, Ohio, as it reevaluates the infrastructure needed to support its growing cloud and AI operations.
The tech giant confirmed it will halt early-stage construction on the Ohio sites, reserving two of the three parcels for farmland instead.
The Ohio pause is part of a broader trend.
Microsoft previously delayed the next phases of a major Wisconsin data center and, according to analysts at TD Cowen, has also scaled back some international plans and canceled U.S. data center leases.