Unions warn about effect on vital services after chancellor confirms job cuts
Unions have warned that as many as 50,000 people could lose their jobs and vital services could deteriorate after Rachel Reeves confirmed plans to cut Civil Service running costs by 15%.
The chancellor said Labour was looking to cut back the Civil Service, which she said had swelled during the Covid-19 pandemic, by slashing its ‘back office functions, the administrative and bureaucracy functions’ by the end of this parliament.
The leader of the biggest civil service union said any cuts will hit frontline services after years of underfunding by previous Conservative governments.
Operations normal on Saturday, Heathrow CEO says
British Airways operates around 90% of flights
Police say incident not being treated as suspicious
Government, Heathrow order separate probes
An investigation into the power outage caused by a substation fire that shut London's Heathrow Airport has been ordered after about 200,000 passengers were affected by its closure.
U.K. Energy Secretary Ed Miliband has ordered the National Energy System Operator to "urgently investigate" the power outage caused by a substation fire, and is working with Ofgem and using powers under the Energy Act to formally launch the grid operator's investigation.
Meanwhile, an internal review of the airport's crisis management plans and its response to Friday's power outage will be undertaken by former transport secretary Ruth Kelly, who is an independent member of Heathrow's board, Heathrow chairman Lord Paul Deighton said.
British Airways said it is expecting to run a "near-full schedule" on Sunday and passengers should go to the west London airport as normal unless told otherwise.
The British government on Saturday ordered an investigation into the country's energy resilience after an electrical substation fire shut Heathrow Airport for almost a day and raised concerns about the UK's ability to withstand disasters or attacks on critical infrastructure.
While Heathrow Airport said it was fully operational on Saturday, thousands of passengers remained stuck, and airlines warned that severe disruption will last for days as they scramble to relocate planes and crews and get travellers to their destinations.
Inconvenienced passengers, angry airlines and concerned politicians all want answers about how one seemingly accidental fire could shut down Europe's busiest air hub.
This is a huge embarrassment for Heathrow airport.
A power outage forced Heathrow Airport to close for much of Friday, resulting in major disruption for passengers flying to and from Europe’s busiest airport.
The power loss was caused by a blaze at an electricity substation in Hayes, west London, late on Thursday.
London Fire Brigade deputy commissioner Jonathan Smith said: “The fire involved a transformer comprising 25,000 litres of its cooling oil fully alight.
“This created a major hazard owing to the still live high voltage equipment and the nature of an oil-fuelled fire.
Heathrow Airport had “enough power” from remaining substations despite Friday’s shutdown, the chief executive of National Grid has said.
John Pettigrew said two substations were “always available for the distribution network companies and Heathrow to take power”.
Flights were halted after a fire knocked out an electricity substation in Hayes on Thursday evening, and were not able to resume until Friday evening.
In his first comments since the disruption, Mr Pettigrew told the Financial Times: “There was no lack of capacity from the substations.
Ministers are “closely monitoring” how airlines look after their passengers following the “unprecedented” Heathrow shutdown, the Transport Secretary has said.
Heidi Alexander said in the Commons that the Government “is acutely aware of the need to ensure that passengers are well looked after”, after around 200,000 passengers were disrupted by the closure.
A fire at the North Hyde electricity substation last week disrupted power supplies at the West London hub.
Ms Alexander said “back-up systems ensured safety and security systems and protocols were maintained at all times”, but these systems – including diesel generators – were not designed to support the airport’s full operations.
Heathrow Airport had "enough power" from remaining substations despite Friday's shutdown, the chief executive of National Grid has said.
John Pettigrew said two substations were "always available for the distribution network companies and Heathrow to take power".
Flights were halted after a fire knocked out an electricity substation in Hayes on Thursday evening, and were not able to resume until Friday evening.
In his first comments since the disruption, Mr Pettigrew told the Financial Times: "There was no lack of capacity from the substations.
(FILES) Passengers arrive with luggage at the Terminal 5 international arrivals hall at London Heathrow Airport in west London on February 14, 2021 .
Britain’s Heathrow airport — Europe’s busiest — shut down early on March 21, 2025 after a major fire at an electricity substation cut power to the sprawling hub, causing disruption worldwide to hundreds of flights and thousands of travellers.
(Photo by JUSTIN TALLIS / AFP)
The head of the UK’s national grid has said there was “enough power” to keep Heathrow Airport running on Friday, after an electrical substation fire shuttered Europe’s busiest air hub.
LONDON (AP) — Heathrow Airport executives on Monday defended their response to a fire that shut down Europe’s busiest air hub for almost a day, after Britain’s energy system operator suggested that the facility had enough electricity from other sources to keep running.
More than 1,300 flights were canceled on Friday after a fire knocked out one of the three electrical substations that supply Heathrow with power.
More than 200,000 passengers had journeys disrupted, and industry experts say the chaos will cost airlines tens of millions of dollars.
The airport reopened after about 18 hours when Heathrow had reconfigured its power supply — something Transport Secretary Heidi Alexander said that “required hundreds of systems to be safely powered down and then safely powered up with extensive testing.”