WASHINGTON, Feb 24., 2025 – Microsoft has reportedly canceled several data center leases with U.S. operators, indicating potentially overbuilt infrastructure and unclear demand for AI services.
The canceled contracts totaled a “couple of hundred MWs,” enough to power two large data centers or more than 100,000 homes for one year.
Investment bank and brokerage firm TD Cowen discovered Microsoft’s move last Friday but said the exact reason for the terminations was unknown.
However, the firm speculated that they could be related to “Microsoft potentially being in an oversupply situation,” meaning the tech giant may have overestimated the demand for AI computing power in previous forecasts.
Last week, Microsoft CEO Satya Nadella made an eyebrow-raising appearance on a podcast dismissing the hype around claims of having achieved "some [artificial general intelligence] milestone" as "nonsensical benchmark hacking."
Most strikingly, Nadella admitted that AI simply hasn't generated much value so far, arguing that economic growth due to the tech would be a much more compelling demonstration of AI's actual accomplishments.
It was an unusually muted response given the tens of billions of dollars the tech giant has poured, and is planning to pour, into the development of AI and the infrastructure to support it — despite real-world applications for the tech remaining few and far between.
Is Nadella worried about a looming dot-com-like bubble that's set to burst?
Microsoft’s stock slipped Monday after an analyst note said it was canceling some US data center leases.
Microsoft’s stock slipped Monday after an analyst note said it was canceling some US data center leases.
The TD Cowen analysts said the pullback may indicate Microsoft is in a “potential oversupply position.”
The TD Cowen analysts said the pullback may indicate Microsoft is in a “potential oversupply position.”
Microsoft said it might make some infrastructure adjustments but still plans to spend over $80 billion on capital expenditures this fiscal year, which ends in June.
Analysts at TD Cowen circulated a note on Friday suggesting that the company has canceled data center leases.
Microsoft said on Monday that it's sticking to its plan to allocate more than $80 billion of its cash to capital expenditures, following an analyst's note on Friday claiming the company has canceled data center leases.
However, Microsoft acknowledged that it "may strategically pace or adjust our infrastructure in some areas."
Microsoft said it might make some infrastructure adjustments but still plans to spend over $80 billion on capital expenditures this fiscal year, which ends in June.
Analysts at TD Cowen circulated a note on Friday suggesting that the company has canceled data center leases.
Microsoft said on Monday that it's sticking to its plan to allocate more than $80 billion of its cash to capital expenditures, following an analyst's note on Friday claiming the company has canceled data center leases.
However, Microsoft acknowledged that it "may strategically pace or adjust our infrastructure in some areas."
Microsoft said it might make some infrastructure adjustments but still plans to spend over $80 billion on capital expenditures this fiscal year, which ends in June.
Analysts at TD Cowen circulated a note on Friday suggesting that the company has canceled data center leases.
Microsoft said on Monday that it's sticking to its plan to allocate more than $80 billion of its cash to capital expenditures, following an analyst's note on Friday claiming the company has canceled data center leases.
However, Microsoft acknowledged that it "may strategically pace or adjust our infrastructure in some areas."
Microsoft said it might make some infrastructure adjustments but still plans to spend over $80 billion on capital expenditures this fiscal year, which ends in June.
Analysts at TD Cowen circulated a note on Friday suggesting that the company has canceled data center leases.
Microsoft said on Monday that it's sticking to its plan to allocate more than $80 billion of its cash to capital expenditures, following an analyst's note on Friday claiming the company has canceled data center leases.
However, Microsoft acknowledged that it "may strategically pace or adjust our infrastructure in some areas."
Microsoft said it might make some infrastructure adjustments but still plans to spend over $80 billion on capital expenditures this fiscal year, which ends in June.
Analysts at TD Cowen circulated a note on Friday suggesting that the company has canceled data center leases.
Microsoft said on Monday that it's sticking to its plan to allocate more than $80 billion of its cash to capital expenditures, following an analyst's note on Friday claiming the company has canceled data center leases.
However, Microsoft acknowledged that it "may strategically pace or adjust our infrastructure in some areas."
Microsoft said it might make some infrastructure adjustments but still plans to spend over $80 billion on capital expenditures this fiscal year, which ends in June.
Analysts at TD Cowen circulated a note on Friday suggesting that the company has canceled data center leases.
Microsoft said on Monday that it's sticking to its plan to allocate more than $80 billion of its cash to capital expenditures, following an analyst's note on Friday claiming the company has canceled data center leases.
However, Microsoft acknowledged that it "may strategically pace or adjust our infrastructure in some areas."
Microsoft said it might make some infrastructure adjustments but still plans to spend over $80 billion on capital expenditures this fiscal year, which ends in June.
Analysts at TD Cowen circulated a note on Friday suggesting that the company has canceled data center leases.
Microsoft said on Monday that it's sticking to its plan to allocate more than $80 billion of its cash to capital expenditures, following an analyst's note on Friday claiming the company has canceled data center leases.
However, Microsoft acknowledged that it "may strategically pace or adjust our infrastructure in some areas."
Microsoft said it might make some infrastructure adjustments but still plans to spend over $80 billion on capital expenditures this fiscal year, which ends in June.
Analysts at TD Cowen circulated a note on Friday suggesting that the company has canceled data center leases.
Microsoft said on Monday that it's sticking to its plan to allocate more than $80 billion of its cash to capital expenditures, following an analyst's note on Friday claiming the company has canceled data center leases.
However, Microsoft acknowledged that it "may strategically pace or adjust our infrastructure in some areas."
Microsoft said it might make some infrastructure adjustments but still plans to spend over $80 billion on capital expenditures this fiscal year, which ends in June.
Analysts at TD Cowen circulated a note on Friday suggesting that the company has canceled data center leases.
Microsoft said on Monday that it's sticking to its plan to allocate more than $80 billion of its cash to capital expenditures, following an analyst's note on Friday claiming the company has canceled data center leases.
However, Microsoft acknowledged that it "may strategically pace or adjust our infrastructure in some areas."
Microsoft said it might make some infrastructure adjustments but still plans to spend over $80 billion on capital expenditures this fiscal year, which ends in June.
Analysts at TD Cowen circulated a note on Friday suggesting that the company has canceled data center leases.
Microsoft said on Monday that it's sticking to its plan to allocate more than $80 billion of its cash to capital expenditures, following an analyst's note on Friday claiming the company has canceled data center leases.
However, Microsoft acknowledged that it "may strategically pace or adjust our infrastructure in some areas."
Microsoft said it might make some infrastructure adjustments but still plans to spend over $80 billion on capital expenditures this fiscal year, which ends in June.
Analysts at TD Cowen circulated a note on Friday suggesting that the company has canceled data center leases.
Microsoft said on Monday that it's sticking to its plan to allocate more than $80 billion of its cash to capital expenditures, following an analyst's note on Friday claiming the company has canceled data center leases.
However, Microsoft acknowledged that it "may strategically pace or adjust our infrastructure in some areas."
After the TD Cowen report on Microsoft data center order cancellations - which we first profiled yesterday for our subscribers, well before Bloomberg - spooked European energy and US AI infrastructure stocks sending them sharply lower, and with the market on the verge of a brutal selloff (as Goldman cautioned last night) it was incumbent on the biggest Mag 7 member to step in... or otherwise the following hockeysticking Mag7 chart would have a very painful reacquaintance with gravity.
Sure enough, while Microsoft was unable to come out and directly refute what TD Cowen said - because it is accurate - Microsoft did damage control using everyone's favorite mouthpiece-for-hire, Jefferies, which in the back of a salesnote, so as to avoid giving it too much prominence even though everyone knew the entire market would read it immediately, the bank said that there has been "a lot of back and forth this weekend post a competitors note / call that highlighted MSFT is cancelling DC leases. Competitor is basically saying that MSFT is cancelling and ORCL is picking up the majority of the capacity."
And so, to give MSFT a chance to respond, but not really respond so it is not in violation of Reg FD or some other materially misleading comment, Jefferies was used as a broken telephone by the 2nd largest company in the world to convey the following message: We’re currently hosting MSFT IR in Sydney, please see below for notes from those discussions.
Thank you to our Australian Equities team for passing these along.