Generating controversy: GRDA seeks $1.6 billion bond capacity hike (opens in a new tab)
In an effort to build two new natural gas units, refurbish a third facility and ultimately add hundreds of megawatts of electricity generation into its portfolio, the Grand River Dam Authority is asking the Oklahoma Legislature to approve a $1.6 billion increase to its bonding capacity. Outlined in House Bill 1422, the request marks the second time in four years that the state-owned public power utility has sought a bonding capacity increase. In 2022, GRDA’s bonding capacity was hiked from $1.41 billion to $2 billion in conjunction with a massive incentive package aimed at luring a Panasonic battery plant to northeast Oklahoma. While the Japanese manufacturer ultimately selected other states for battery plants and no state incentive payments were triggered, the situation did authorize the nearly $600 million increase in GRDA’s bonding capacity, which the non-appropriated agency used to finance its new natural gas “Unit 4” currently under construction.